Elbow Lake Divison Street Reconstruction

Project Information

  • Reconstruction Utility and Surface Infrastructure on Division Street West (CSAH 1) and a Portion of 3rd  Avenue SW

Estimated Project Schedule

  • Award Construction Contract- June 4, 2018
  • Commence Construction- July 16, 2018
  • Substantially Complete Construction – October 2018
  • Finalize Construction- June 2019
  • Project Closeout- August 2019

Future Traffic Impact

  • Road closed to thru traffic during construction
  • Detour Map

Benefits

  • Sanitary Sewer and Water System Improvements
  • Surface and Drainage Improvements

Cost Estimate

  • Approximately $1.9 million
  • Grant County will fund costs to surface and infrastructure  being constructed within CSAH 1 Right-of-Way
  • Grant County will fund costs related to storm sewer infrastructure improvements
  • The City of Elbow Lake will fund costs related to surface infrastructure  on 3rd Avenue SE
  • The City of Elbow Lake will fund costs related to the improvement of water distribution and sanitary sewer collection systems

Division Street